Streets
There are 82 miles of streets in the City of Diamondhead. In 2018, the City hired SMPDD and CivilLink Engineering to analysis the condition of the streets and grade each street using the PACER scale rating. This report is used by the City to determine which streets are paved each year. The city budgets approximately $500,000 annually for street paving.
2025 Street Paving Project
Bayou Drive
Lola Drive
Turnberry Drive, Way, & Court
Below is the updated schedule for this project.
Bayou Drive | Lola Drive | Turnberry | |
Base Repair | 6/25-7/10 | 7/14 - 7/22 | 7/23 - 7/29 |
Paving | 7/21 - 7/30 | 07/31 | 8/1 |
Striping | 8/6 - 8/7 | 8/11 - 8/12 | 8/13 - 8/14 |